Corpus Christi, TX, USA – The U.S. Army Corps of Engineers (USACE) on Friday awarded a $139 million construction contract to Great Lakes Dredge & Dock Company, LLC. (GLDD), to complete the third phase of the landmark Port of Corpus Christi Ship Channel Improvement Project (CIP). The four-phase infrastructure project will increase the Corpus Christi Ship Channel depth from -47 feet Mean Lower Low Water (MLLW) to -54 feet MLLW and widen it to 530 feet, with an additional 400 feet of barge shelves.
Phase 3 will extend west of the La Quinta Junction through the Chemical Turning Basin in the Port’s Inner Harbor. GLDD completed the first phase of the CIP on time in March 2020, deepening and widening the waterway from the Gulf of Mexico to Harbor Island. In April 2020, the Phase 2 contract was awarded to Callan Marine Ltd., and is currently under construction, deepening and widening the channel from Harbor Island to 2.7 miles past the La Quinta Junction and includes Ingleside. In Ingleside, three large crude export marine terminal operators – Buckeye Partners, Moda Midstream and Flint Hills Resources – currently operate.
“The Texas Coast has a vibrant natural ecosystem, and our coastline provides vast economic, social and environmental benefits to the nation,” said U.S. Army Corps of Engineers Galveston District Commander Col. Tim Vail. “The economic benefits associated with this project are vital to the region. The Port of Corpus Christi is already responsible for more than 98,000 regional jobs, and the completion of this channel improvement project will lead to additional jobs, allowing for increased funding into community reinvestment initiatives. The enhanced channel will also improve safety and efficiency by allowing two-way traffic, and a safer passthrough for deep-draft vessels.”
The CIP is a long anticipated collaboration between the Port of Corpus Christi, U.S. Army Corps of Engineers and the federal government. For more than 30 years, the Port of Corpus Christi has campaigned for federal funds to bring the CIP to fruition. To date, the port has provided $161.5 million for its portion of the total project cost share, with the federal government appropriating $296.3 million dollars thus far in funding.
“The Port of Corpus Christi applauds the U.S. Army Corps of Engineers for continuing to move expeditiously on this nationally vital waterway project,” said Sean Strawbridge, Chief Executive Officer for the Port of Corpus Christi. “Advancing the third phase of this historic initiative in developing critical coastal navigation infrastructure reinforces our nation’s importance in serving the global energy markets, and certainly solidifies the Port of Corpus Christi’s position as the largest energy export gateway in the United States. We welcome Great Lakes Dredge and Dock back to the project and have every confidence they will complete the work on time and on budget.”
Great Lakes Dredge & Dock has extensive experience working on high-profile marine projects over its 128 years in business, including the Deepwater Horizon Oil Spill cleanup and the deepening of the Port Miami harbor.
“We are proud to partner with the USACE, Galveston District, the Port of Corpus Christi and local officials in the execution of Phase 3 of the Corpus Christi deepening project,” said Lasse Petterson, Chief Executive Officer for Great Lakes Dredge & Dock Company. “Great Lakes’ proven experience in this type of project, our high safety standards and our expertise in minimizing environmental impact in the areas we work will support our goal of completing this project safely, on time and within budget.”
Estimated completion for the third phase of the Corpus Christi Ship Channel Improvement Project is June 2023.
关于科珀斯克里斯蒂港管理局
As the leading U.S. Crude Oil export ports and a major economic engine of Texas and the nation, the Port of Corpus Christi is the largest port in the United States in total revenue tonnage. Strategically located on the western Gulf of Mexico with a 36-mile, soon to be 54-foot (MLLW) deep channel, Port of Corpus Christi is a major gateway to international and domestic maritime commerce. The Port has excellent railroad and highway network connectivity via three North American Class-1 railroads and two major interstate highways. With an outstanding staff overseen by its seven-member commission, Port of Corpus Christi is “Moving America’s Energy.”
www.portofcc.com
About Great Lakes Dredge and Dock
大湖疏浚与码头公司(“大湖公司”或“本公司”)是美国最大的疏浚服务提供商,也是唯一一家在海外拥有大规模业务的美国疏浚公司。本公司还是陆地和水域环境及修复服务的重要提供商。本公司在估算、生产和项目管理部门均配备了经验丰富的土木、海洋和机械工程技术人员。 在超过128年的发展历程中,本公司从未出现过未能完成海上项目的记录。大湖公司为工程师设立了严谨的培训计划,确保他们在公司运营中逐步晋升时,能够凭借实践经验发挥出色表现。公司的“零事故、零伤害”(IIF®)安全管理计划已融入企业文化的方方面面。公司对IIF®文化的承诺,营造了一种将员工安全置于首位的的工作环境。 大湖公司还拥有并运营着美国疏浚行业中规模最大、类型最齐全的船队,由200多艘专用船舶组成。
• 在社交媒体上关注“美洲能源港”•
###